2024/20/04
Monitoring the Construction of High-mast Lighting in RBN Villages
Project Status:
Completed
Project Number: 2138
Project Scope:

To monitor the construction of high-mast lighting in Royal Bafokeng Nation (RBN), done by Rustenburg Local Municipality (RLM) to ensure that it is of good standard and the positioning is aligned with the RBN cadastral maps. Monitoring will be done by means of reviewing and analysing progress reports and attending site meetings throughout the duration of the project that will come to conclusion on 21 July 2016.  

In scope:

  • Identification of the positioning of lights;
  • Approval of design plans;
  • Approval of time frame;
  • Monitoring construction ( Attending site meetings and conducting random inspections); and 
  • Project handover.
Key Focus Area: Public & Community Utilities
Focus Areas: Safety and Security
Beneficiaries: Community
Regions: North Region, Central Region, South East Region
Villages: Kanana, Serutube, Marakana & Mosenthal, Mabitse, Tlapa & Tlapa East, Rasimone, Lesung, Mafika, Robega
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Thursday 21 January 2016
Baseline End Date: Friday 12 August 2016
Actual Start Date: Thursday 21 January 2016
Actual End Date: Thursday 5 October 2017
Schedule Variance:
-419 days
-205.392 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 5
Total: 5