Rehabilitation of upgraded roads and storm water structures in RBN-2017
Project Status:
Completed
Project Number: 2363
Project Scope:

To coordinate the rehabilitation of upgraded roads and storm water structures in RBN. The process includes tendering process for the appointment of an ideal service provider. The project intends to ensure that all the roads in RBN are maintained to a standard that they will be safe to be utilised by everyone. The project will be completed in December 2017.

In scope:

  • Procurement of Precast Concrete Storm Water Pipes
  • Tendering process
  • Maintenance of the roads
  • Project handover and project completion.
Key Focus Area: Public & Community Utilities
Focus Areas: Health and Social Development, Economic Development, Safety and Security
Beneficiaries: Community
Regions: North Region, North East Region, South East Region, Capital Region, Central Region
Villages: Phokeng, Lefaragatlha, Tlaseng, Thekwane, Mogono, Kanana, Marakana & Mosenthal, Tsitsing, Lesung
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 3 July 2017
Baseline End Date: Wednesday 11 April 2018
Actual Start Date: Monday 3 July 2017
Actual End Date: Tuesday 1 May 2018
Schedule Variance:
-20 days
-7.092 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 2
Total: 2