2024/28/03
Monitoring the construction of Internal Road and storm water in Kanana
Project Status:
Completed
Project Number: 2375
Project Scope:

To monitor the construction of roads and storm water done by Impala Platinum Mine Limited to ensure that it is of good standard and due process is being followed. The 0.65km road is being constructed to upgrade existing gravel roads in Kanana village. This will be accomplished by making use of consultants (Civil engineers) and a contractor with a CIDB grading of no less than six.

Since the road is being constructed on the Royal Bafokeng Nation's (RBN) land, the administration has a vested interest therein. The project manager from the RBN Infraco department will monitor the project through means of receiving and analysing progress reports and attending site meetings throughout the duration of the project that will come to conclusion on 03 December 2017.  

In scope:

  • Community awareness and involvement;
  • Approval of road construction and constructions designs;
  • Approval of borrow and spoil sites and rehabilitation plan;
  • Approval of programme of works (Start to Completion);
  • Monitoring construction process (Site meetings including progress reports); and
  • Project handover including as built drawings.
Key Focus Area: Public & Community Utilities
Focus Areas: Safety and Security, Public & Community Utilities
Beneficiaries: Community, South African Government
Regions: Central Region
Villages: Kanana
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Thursday 3 August 2017
Baseline End Date: Friday 1 December 2017
Actual Start Date: Thursday 3 August 2017
Actual End Date: Wednesday 14 February 2018
Schedule Variance:
-75 days
-62.5 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 1
Total: 1