Know Your Kgotla
Project Status:
Cancelled
Project Number: 2382
Project Scope:

To design 72 profiles of different Makgotla structures in the Bafokeng through a series of interviews across all the regions.  The interviews will be conducted by Bafokeng volunteers who will be paid a stipend.  A set of questions will be created which will be administered by these volunteers.  The project will run from the June to September 2019.

In Scope

  • Questionnaire design;
  • Sourcing permission from Governance;
  • Recruitment if volunteers;
  • Interviews;
  • Data analysis; and
  • Profile compilation.
Key Focus Area: Governance & Administration
Focus Areas:
Beneficiaries: Community
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Office of the Group COO
Progress Actual: 0 %
Progress Planned: 0 %
Baseline Start Date: Friday 1 June 2018
Baseline End Date: Thursday 3 January 2019
Actual Start Date: Friday 1 June 2018
Actual End Date: Thursday 3 January 2019
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
22.703 %
Risks: 0
Issues: Unresolved: 0
Resolved: 0
Total: 0