Dumela Phokeng June 2018
Project Status:
Completed
Project Number: 2406
Project Scope:

Dumela Phokeng is an initiative that gives leadership a chance to visit the nation's 5 regions to afford Bafokeng an opportunity to voice out their concerns and needs. The event will be held in the 5 Royal Bafokeng Nation (RBN) regions and Traditional Council will conduct presentations to the constituencies. The events will take place as follows; Capital Region on the 2nd of June 2018, Central region on the 3rd of June 2018,  orth East on the 9th June 2018, Sth East on the 10th June 2018 and North A and North B region on the 23rd and 24th June 2018. 

  • Establish the committee with dedicated project managers;
  • Venues big enough for potentially 700 participants.
  • An effective sound system to communicate to 700 people, PA systems;
  • Tent for catering;
  • Volunteers to assist with selected event proceedings;
  • Marketing of the event through radio announcements, Flyers and announcements at Mokgotla meetings by Dikgosana (Headsmen);
  • Transport for every village;
  • Catering lunch for an estimated 700 attendees;
  • A company to manage waste;
  • Security monitored and maintained during events;
  • A programme for the events;
  • Registration of all attendees per region;
  • Arrange photographer and videographer;
  • Arrange Emergency Services.
Key Focus Area: Governance & Administration
Focus Areas: Governance & Administration
Beneficiaries: Community
Regions: North Region, Central Region, North East Region, South East Region, Capital Region
Villages: Phokeng, Luka, Chaneng, Kanana, Photsaneng, Tsitsing
Institutions: Secretary of Traditional Governance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 15 May 2018
Baseline End Date: Friday 29 June 2018
Actual Start Date: Tuesday 15 May 2018
Actual End Date: Friday 29 June 2018
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
19.206 %
Risks: 3
Issues: Unresolved: 0
Resolved: 4
Total: 4
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found