The first phase refurbishment of the former TEBA Offices to accommodate the establishment of the RBI STEAM Centre
Project Status:
On hold
Project Number: 2599
Project Scope:

The former TEBA buildings and site have been unoccupied for two years.  This project will undertake a basic renovation of these premises with the view to establishing the RBI STEAM centre there in 2020.

The scope of work will include:

-       Stripping out redundant network and communications cabling

-       Repairs and upgrades to the water reticulation, plumbing and guttering.

-       Stripping off flaking paint and repainting of the interior of buildings

-       Repainting of facia boards, eves timber, guttering and windows

-       Repainting of the external steel structures

-       Minor building alterations

-       Complete refurbishment of the ablution block

-       Tiling or retiling of toilet facilities where needed

-       Repairs or replacement of doors, skirting boards, eves timber and ceiling boards where needed

-       Installation of a kitchenette in the Staff Centre

-       Bush cutting, tree trimming and site cleanup.

-       Establishing basic electricity supply.  (Proper review and repairs of the electrical reticulation is not included in this scope)

Key Focus Area: Education and Skills Development
Focus Areas: Education and Skills Development
Beneficiaries: Principals, Teachers, Children
Regions: Capital Region
Villages: Phokeng
Institutions: Royal Bafokeng Institute (RBI)
Progress Actual: 31.6 %
Progress Planned: 100 %
Baseline Start Date: Thursday 15 August 2019
Baseline End Date: Wednesday 18 December 2019
Actual Start Date: Thursday 15 August 2019
Actual End Date: Friday 31 July 2020
Schedule Variance:
-226 days
-180.8 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 4
Issues: Unresolved: 0
Resolved: 5
Total: 5