Milestone name |
Milestone indicator |
Responsible person |
Baseline date |
Actual date |
Approve budget for project | Budget approved | Lerato Motaung | Wednesday 25 August 2010 | Wednesday 25 August 2010 |
Grant scoping consultants go ahead to commence | Consultants commence their work | Lerato Motaung | Wednesday 25 August 2010 | Wednesday 25 August 2010 |
Meet with SAHA | Meeting with SAHA held and debriefing held to discuss outcomes of the discussion.
Lerato Motaung notified by Totem | Lerato Motaung | Wednesday 25 August 2010 | Wednesday 25 August 2010 |
Meet with SAHRA | Meeting with SAHRA held and debriefing held to deliberate on outcomes of the meeting
Lerato Motaung notified by Totem | Lerato Motaung | Monday 30 August 2010 | Monday 30 August 2010 |
Conference Call with WGBH | Conference call held between Francis Gerard and WGBH. Outcomes of discussion noted and report sent through to Lerato Motaung by Totem. | Lerato Motaung | Wednesday 13 October 2010 | Wednesday 13 October 2010 |
Proposal received by Research & Planning Department | Proposal document written and sent to Lerato Motaung. Passed on to Dr. Sue Cook for deliberation, consultation and decision. | Lerato Motaung | Friday 29 October 2010 | Friday 29 October 2010 |
Meet with DISA | Meeting with DISA held and debriefing session held to deliberate on outcomes of the meeting.
Lerato Motaung notified by Totem. | Lerato Motaung | Tuesday 30 November 2010 | Tuesday 30 November 2010 |
Meet with UKZN | Meeting with UKZN Ulwazi Programme held. Deliberation on outcomes held.
Lerato Motaung notified by Totem. | Lerato Motaung | Tuesday 30 November 2010 | Tuesday 30 November 2010 |