2010 feeding plan & budget for ongoing fed schools  2010 feeding plan & budget for ongoing fed schools in place.  Segoe 0838811799 Wednesday 20 January 2010 Wednesday 20 January 2010 
Project Planning   Project Charter Workplan in place  Hlalela Mathonsi Saturday 30 January 2010 Saturday 30 January 2010 
Mobilise and engage stakeholders   Stakeholder map Communication plan Engagement plan Training material Facilitated workshop and forums  Hlalela Mathonsi Sunday 28 February 2010 Sunday 28 February 2010 
Roll out feeding scheme to 10 schools  Schools utensils and infrastructure needs analysis Utensils procured and delivered to schools Infrastructure upgrades completed at schools Delivery model developed and syndicated with stakeholders Service providers appointed Food handlers recruited, appointed and trained Schools on boarded into the feeding scheme  Hlalela Mathonsi Thursday 1 April 2010 Thursday 1 April 2010 
Start feeding 10 schools 10 schools feed. Hlalela Mathonsi Monday 5 April 2010 Monday 5 April 2010 
Monitoring of food distribution for the 1st 10 schools. Report received on Monitoring of food distribution. Hlalela Mathonsi Thursday 10 June 2010 Thursday 10 June 2010 
Mobilise and engage stakeholders for 2nd batch of schools   Mobilised and engaged stakeholders for 2nd batch of schools.  Segoe 0838811799 Thursday 1 July 2010 Thursday 1 July 2010 
Conduct a survey and roll out to 10 additional schools Survey Conducted and rolled out to 10 additional schools. Hlalela Mathonsi Thursday 16 September 2010 Thursday 16 September 2010 
Final agreement with NW DoE   Sign service level agreement on claiming process on NSNP funds  Segoe 0838811799 Wednesday 22 September 2010 Wednesday 22 September 2010 
Project Conclusion  Project Concluded.  Segoe 0838811799 Friday 26 November 2010 Friday 26 November 2010 
Showing 1 to 10 of 16 Pages: 1 2