Construction of a three-classroom block at Bafokeng High of approximately 292m2 floor area; and the construction of a staff-room at Thethe High of approximately 130m2 floor area. Both projects are to be completed by March 2010.
Key Focus Area:
Education and Skills Development
Focus Areas:
Education and Skills Development, Public & Community Utilities
Beneficiaries:
Children
Regions:
Capital Region, North Region
Villages:
Kgale, Luka
Institutions:
Infrastructure Maintenance
Progress Actual:
100 %
Progress Planned:
100 %
Baseline Start Date:
Tuesday 6 October 2009
Baseline End Date:
Wednesday 10 February 2010
Actual Start Date:
Monday 12 October 2009
Actual End Date:
Monday 1 March 2010
Schedule Variance:
-19 days -14.961 %
Approved Total Budget:
Hidden
Total Expenditures:
Hidden
Estimated to Complete:
Hidden
Total at Completion:
Hidden
Budget Variance:
Hidden 0 %
Risks:
1
Issues:
Unresolved: 0 Resolved: 0 Total: 0
Addition of staffrooms and classrooms at Thethe and Bafokeng high schools