Maintenance plan for Bafokeng Sports Campus ("BSC")
Programme Status:
Completed
Programme Number: 356
Programme Executive Summary (Scope):

To maintain the BSC infrastrucuture so that it operates effectively and efficiently.

 

IN SCOPE:-

  • To ensure that the AC & DC power supply systems are in good working condition at all times.
  • To ensure that the electrical utilities are in good working condition at all times.
  • To ensure that the building structure's internal systems are in good working condition at all times.
  • To ensure that the building structure's external systems are in good working condition at all times.
  • To ensure that the plumbing systems are in good working condition at all times.
  • To ensure that the fire-fighting, safety & security systems are in good working condition at all times.
  • To ensure that the acquatic facilities are in good working condition at all times.
  • To ensure that the housekeeping systems are in good working condition at all times.
  • To ensure that the waste management systems are in good working condition at all times.
Key Focus Area: Sport Development
Focus Areas: Public & Community Utilities
Beneficiaries: Community
Regions: Capital Region
Villages: Phokeng
Institutions: Royal Bafokeng Sports (RBS)
Baseline Start Date: Sunday 10 April 2011
Actual Start Date: Friday 15 April 2011
Approved Annual Budget: Hidden
Budget Variance:
2024 Year to date budget: Hidden
2024 Year to date expenses: Hidden
2024 Budget variance to date: 0 %
2024 Percentage of annual budget spent: 0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 12
Total: 12