The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/07/05
Maintenance plan for Royal Bafokeng Sports Palace ("RBSP")
Programme Status:
Completed
Programme Number: 357
Programme Executive Summary (Scope):

To maintain the RBSP infrastructure so that it operates effctively and efficiently.

IN SCOPE:

  • To ensure that the AC & DC power supply systems are in good order at all times.
  • To ensure that the electrical utilities are in good working condition at all times.
  • To ensure that the building structure's interior systems are in good working condition at all times.
  • To ensure that the building structure's exterior systems are in good working condition at all times.
  • To ensure that the plumbing systems are in god working condition at all times.
  • To ensure that the fire-fighting, safety, & security systems are in good working condition at all times.
  • To ensure that the acquatic facilities systems are in good working condition at all times.
  • To ensure that the housekeeping systems are in good working condition at all times.
  • To ensure that the waste management systems are in good working condition at all times.
Key Focus Area: Sport Development
Focus Areas: Public & Community Utilities
Beneficiaries: Community
Regions: Capital Region
Villages: Phokeng
Institutions: Royal Bafokeng Sports (RBS)
Baseline Start Date: Sunday 10 April 2011
Actual Start Date: Friday 15 April 2011
Approved Annual Budget: Hidden
Budget Variance:
2024 Year to date budget: Hidden
2024 Year to date expenses: Hidden
2024 Budget variance to date: 0 %
2024 Percentage of annual budget spent: 0 %
Risks: 0
Issues: Unresolved: 0
Resolved: 10
Total: 10
Objectives

Issues

Risks

No files found

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION