Construction of Roads (from gravel to paved) and Stormwater (installation of stormwater pipes and channels) of various roads in Kanana, Tlaseng, Thekwane and Motsitle Village by 6 April 2010.
Key Focus Area:
Public & Community Utilities
Focus Areas:
Public & Community Utilities
Beneficiaries:
Community, Other
Regions:
Central Region, North East Region
Villages:
Kanana, Tantanana, Tlaseng, Thekwane, Serutube, Tlapa & Tlapa East
Institutions:
Infrastructure Maintenance
Progress Actual:
100 %
Progress Planned:
100 %
Baseline Start Date:
Tuesday 6 October 2009
Baseline End Date:
Monday 31 January 2011
Actual Start Date:
Thursday 10 September 2009
Actual End Date:
Monday 31 January 2011
Schedule Variance:
0 days 0 %
Approved Total Budget:
Hidden
Total Expenditures:
Hidden
Estimated to Complete:
Hidden
Total at Completion:
Hidden
Budget Variance:
Hidden 0 %
Risks:
3
Issues:
Unresolved: 0 Resolved: 8 Total: 8