Construction of a new school for the Royal Bafokeng Nation consisting of the following: Foundation School, Intermediate School, High School by July 2010.
Key Focus Area:
Education and Skills Development
Focus Areas:
Education and Skills Development, Public & Community Utilities
Beneficiaries:
Children
Regions:
Capital Region
Villages:
Phokeng
Institutions:
Infrastructure Maintenance
Progress Actual:
100 %
Progress Planned:
100 %
Baseline Start Date:
Thursday 4 September 2008
Baseline End Date:
Thursday 1 July 2010
Actual Start Date:
Thursday 4 September 2008
Actual End Date:
Sunday 5 September 2010
Schedule Variance:
-66 days -9.925 %
Approved Total Budget:
Hidden
Total Expenditures:
Hidden
Estimated to Complete:
Hidden
Total at Completion:
Hidden
Budget Variance:
Hidden 0 %
Risks:
9
Issues:
Unresolved: 0 Resolved: 1 Total: 1
Construction of new Lebone II - School of Excellence