Project Status:
Completed
Project Number: 127
Project Scope:
To facilitate and implement additional software development on the RBN Operations Room website by end of June 2011.
 
In Scope:
  • A programmes section on the MPS (Manage-by-Projects/Programmes System;
  • automated Gantt and Activity charts;
  • automated Cost/benefit analysis;
  • automated Close-out reports;
  • automated PMO Monthly Reports;
  • automated OPSCOM reports;
  • automated project reports;
  • integration with finance;
  • contract tracking system;
  • notification e-mails;
  • a detailed interactive Events Calendar; and
  • an online budget approval system.

Additions/changes to scope:

  • Events calendar RAGs
  • Events calendar minutes
  • Programme objectives, KPAs and KPIs
  • Automated budget submission and approval system
Key Focus Area: Other
Focus Areas: Other
Beneficiaries: Community, RBN Employees, Other
Regions: Capital Region
Villages: Phokeng
Institutions: Organisational Performance & Project Management Office (OPMO)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 12 April 2010
Baseline End Date: Wednesday 31 August 2011
Actual Start Date: Monday 12 April 2010
Actual End Date: Monday 3 October 2011
Schedule Variance:
-33 days
-6.522 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
8.307 %
Risks: 8
Issues: Unresolved: 0
Resolved: 3
Total: 3
Operations Room (Phase 2) additional software development
Gis_map_legend

Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Rated: No Votes
Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION