2024/02/05
Ananda Entertainment Park
<< Back
Project Status:
Completed
Project Number: 131
Project Scope:
To establish an Entertainment Arena and Art and Craft Market with the aim of creating business and employment opportunities for local SMME's and the local communities during the 2010 FIFA World Cup.
Key Focus Area: World Cup 2010
Focus Areas: World Cup 2010
Beneficiaries: Other
Regions: Capital Region
Villages: All Villages, Phokeng
Institutions: Royal Bafokeng Enterprise Development (RBED)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 1 February 2010
Baseline End Date: Saturday 31 July 2010
Actual Start Date: Monday 1 February 2010
Actual End Date: Saturday 31 July 2010
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 5
Issues: Unresolved: 0
Resolved: 2
Total: 2
Entertainment Arena and the Art and Craft Market
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Rated: No Votes
Tags:
 