Construction and Upgrading of Roads and Stormwater in Kgale and Lefaragatlhe Villages
In Scope:
KGALE: Approximately 0.865km will be surfaced by the placing of 60mm interlocking block paving along with Fig. 8c kerbs and edge-beams.
LEFARAGATLHE: Road 1 which is approximately 1.122km will be surfaced by the placing of 60mm interlocking block paving along with Fig. 8c kerbs and edge-beams.
LEFARAGATLHE: Road 2 which is approximately 0.430km will be surfaced by the placing of 60mm interlocking block paving along with Fig. 8c kerbs and edge-beams.
Key Focus Area:
Public & Community Utilities
Focus Areas:
Public & Community Utilities
Beneficiaries:
Community
Regions:
Capital Region
Villages:
Kgale, Lefaragatlha
Institutions:
Infrastructure Maintenance
Progress Actual:
100 %
Progress Planned:
100 %
Baseline Start Date:
Tuesday 8 June 2010
Baseline End Date:
Wednesday 10 November 2010
Actual Start Date:
Tuesday 8 June 2010
Actual End Date:
Wednesday 10 November 2010
Schedule Variance:
0 days 0 %
Approved Total Budget:
Hidden
Total Expenditures:
Hidden
Estimated to Complete:
Hidden
Total at Completion:
Hidden
Budget Variance:
Hidden 0 %
Risks:
0
Issues:
Unresolved: 0 Resolved: 0 Total: 0
Construction and Upgrading of Roads and Stormwater in Kgale and Lefaragatlhe