Scope statement: To Upgrade bulk water distribution main lines in the Capital region in order to improve water supply capacity by revamping the existing water reticulation networks by the 25 March 2011.
In scope:
Setting out;
Excavations;
Pipe laying;
Ancillaries;
chambers; and
Testing.
Scope change/additions:
Infrastructure department approved the installation of valves requested by Rand Water. The material will only be delivered after the 13 May 2011 to complete the additional scope of work approved in VO9. The project end date has been extended to the 03 June 2011.