Phokeng bulk water distribution
Project Status:
Completed
Project Number: 178
Project Scope:

Scope statement: To Upgrade bulk water distribution main lines in the Capital region in order to improve water supply capacity by revamping the existing water reticulation networks by the 25 March 2011.

In scope:

  • Setting out;
  • Excavations;
  • Pipe laying;
  • Ancillaries;
  • chambers; and
  • Testing.

Scope change/additions:

Infrastructure department approved the installation of valves requested by Rand Water. The material will only be delivered after the 13 May 2011 to complete the additional scope of work approved in VO9. The project end date has been extended to the 03 June 2011.

Key Focus Area: Public & Community Utilities
Focus Areas: Public & Community Utilities
Beneficiaries: Community
Regions: Capital Region
Villages: Kgale, Lefaragatlha, Phokeng
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 20 September 2010
Baseline End Date: Tuesday 7 June 2011
Actual Start Date: Monday 20 September 2010
Actual End Date: Tuesday 7 June 2011
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 0
Issues: Unresolved: 0
Resolved: 6
Total: 6