2024/14/05
Collection/crush pens 2015
Project Status:
Completed
Project Number: 1946
Project Scope:

To create an enabling environment to Bafokeng stock farmers by erecting crush pens for livestock at their grazing areas. Many local farmers struggle with accessibility to crush pens, thus this project will largely benefit them.   All 8 crush pens will be erected  by end of November 2015. A consultant will be appointed to erect the crush pens. The crush pen will be erected in the farms within 3 Bafokeng regions, and farmers will be expected to share the pens.

In scope:

  • Appointment of contractors
  • Site inspection with the contractors
  • Procuremenet of the crush pens
  • Erection of the crush pens
  • Site handover
Key Focus Area: Environmental Management
Focus Areas: Economic Development, Food Security, Public & Community Utilities, Environmental Management
Beneficiaries: Community, Bafokeng SMME's
Regions: Central Region, North East Region, Capital Region, South East Region
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega
Institutions: Land use management
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 4 August 2015
Baseline End Date: Saturday 12 September 2015
Actual Start Date: Tuesday 4 August 2015
Actual End Date: Monday 29 February 2016
Schedule Variance:
-170 days
-435.897 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
-33.333 %
Risks: 2
Issues: Unresolved: 0
Resolved: 3
Total: 3
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 