Project Status:
Completed
Project Number: 1996
Project Scope:

To facilitate a mental health workshop in Phokeng. The aim is to bridge the gap between primary health care services and hospital services for mental health care users. There seems to be many issues regarding admission, counselling and discharging mental health care givers between health care services and the hospital and this will be part of the discussion in the workshop. There will be stakeholders to address everyone who will be attending and participating in the workshop. The mental health coordinator, with the assistance of the caregivers, will plan and facilitate the workshop. The date for the campaign is the 22nd of October 2015.

In scope:

  • BriefingĀ of the multidisciplinary team members.
  • Invite stakeholders
  • Procurement of promotional materials
  • Organising pamphlets for information
  • Organise logistics
  • Facilitate the workshop
Key Focus Area: Health and Social Development
Focus Areas: Education and Skills Development, Health and Social Development, Economic Development
Beneficiaries: Other
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Health & Social Development Services (HSDS)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 17 August 2015
Baseline End Date: Thursday 22 October 2015
Actual Start Date: Monday 17 August 2015
Actual End Date: Thursday 22 October 2015
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
88.428 %
Risks: 3
Issues: Unresolved: 0
Resolved: 0
Total: 0