The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/14/05
Makgotla Consultations
Project Status:
Completed
Project Number: 2046
Project Scope:

To coordinate a series of events for community consultations on the development of a Royal Bafokeng Nation's (RBN) land policy. The events will be held in five RBN regions for community to give their inputs on the development of the policy. Coordination of the event will be done by a selected steering committee and dedicated project manager. The project will run from 15 September to 20 October 2015, with events taking place as follows; Capital region on 3 October 2015, South East region on 4 October 2015; North A and B on 10 October 2015; Central region on 11 October 2015 and lastly North East on 17 October 2015.

In Scope

  • Establish the committee with dedicated project managers;
  • Venues big enough for potentially 500 participants;
  • An effective sound system to communicate to 500 people, PA systems;
  • Tent for catering at North B region;
  • Volunteers to assist with selected event proceedings;
  • Marketing of the event through SMSs, posters and flyers;
  • Transport for every village;
  • Catering lunch for an estimated 500 attendees;
  • Security monitored and maintained during events;
  • A programme for the events;
  • Registration of all attendees per region; and
  • Emergency Services available for minor and major emergencies.
Key Focus Area: Governance & Administration
Focus Areas: Economic Development, Food Security
Beneficiaries: Community
Regions: North Region, Central Region, North East Region, South East Region, Capital Region
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega
Institutions: Secretary of Traditional Governance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 15 September 2015
Baseline End Date: Monday 19 October 2015
Actual Start Date: Tuesday 15 September 2015
Actual End Date: Monday 26 October 2015
Schedule Variance:
-7 days
-20.588 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
31.719 %
Risks: 3
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION