2024/15/05
Cleaning of Luka and Saron Reservoirs
Project Status:
Completed
Project Number: 2136
Project Scope:

Cleaning of the Luka and Saron Reservoirs to minimise/eliminate bacteria growing in the water. A specialised service provider will be appointed to clean the walls and the floors of the reservoirs with high pressure washers. Following that a Photographic and Technical assessment Report on the reservoirs will be handed in upon completion of the project on the 11th of December 2015 by the service provider.

In scope:

  • Empty reservoirs;
  • Pressure clean the inside walls, floors and roof;
  • Assessment of the status of the reservoir (Inside and outside) by structural engineer; and 
  • Refill and disinfect the reservoirs.
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Community, Bafokeng SMME's, RBN Employees
Regions: North Region, Capital Region
Villages: Phokeng, Luka
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 1 December 2015
Baseline End Date: Friday 11 December 2015
Actual Start Date: Tuesday 1 December 2015
Actual End Date: Friday 11 December 2015
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 0
Total: 0