2020/27/10
Telemetry Management System
Programme Status:
Approved Active
Programme Number: 251
Programme Executive Summary (Scope):

To minimize loss of water, care for and protect water resources and ensure efficient and effective use of water.

In Scope:

  • Installation of mechanical flow meters with pulse output and register reed switch; and
  • Installation of level sensors in all Royal Bafokeng Nation reservoirs.
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Community
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Infrastructure Maintenance
Baseline Start Date: Thursday 13 January 2011
Actual Start Date: Thursday 13 January 2011
Approved Annual Budget: Hidden
Budget Variance:
2020 Year to date budget: Hidden
2020 Year to date expenses: Hidden
2020 Budget variance to date: 0 %
2020 Percentage of annual budget spent: 0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 3
Total: 3