The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
Royal Bafokeng Nation Projects Royal Bafokeng Nation Programmes Royal Bafokeng Organisational Performance Mainmenu_programmes2_up The Royal Bafokeng Business Portal
 
2018/19/12
Telemetry Management System
Programme Status:
Approved Active
Programme Number: 251
Programme Executive Summary (Scope):

To minimize loss of water, care for and protect water resources and ensure efficient and effective use of water.

In Scope:

  • Installation of mechanical flow meters with pulse output and register reed switch; and
  • Installation of level sensors in all Royal Bafokeng Nation reservoirs.
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Community
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Infrastructure Maintenance
Baseline Start Date: Thursday 13 January 2011
Actual Start Date: Thursday 13 January 2011
Approved Annual Budget: Hidden
Budget Variance:
2018 Year to date budget: Hidden
2018 Year to date expenses: Hidden
2018 Budget variance to date: 0 %
2018 Percentage of annual budget spent: 0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 3
Total: 3
Objectives

Issues

Risks

No files found

Tags:
 
All Rights Reserved | Copyright © 2018 - ROYAL BAFOKENG NATION