2024/29/04
Shared Services Satisfaction Survey
Project Status:
Completed
Project Number: 2221
Project Scope:

A pilot project intended to monitor and measure, over time, the progress of shared services group. This will be done by developing a questionnaire that will be administered to managers and executives. A report will be compiled on the feedback from the questionnaire results to be disseminated internally. The project will run from April 2016 to August 2016.

In Scope:

  • Literature review;
  • Interview Shared Services group staff;
  • Design and administer questionnaire; and 
  • Compile report.
Key Focus Area: Governance & Administration
Focus Areas: Other
Beneficiaries: RBN Employees
Regions: Capital Region
Villages: Phokeng
Institutions: Research
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Thursday 21 April 2016
Baseline End Date: Monday 5 September 2016
Actual Start Date: Thursday 21 April 2016
Actual End Date: Thursday 1 December 2016
Schedule Variance:
-87 days
-63.504 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 2
Total: 2