The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
Royal Bafokeng Nation Projects Royal Bafokeng Nation Programmes Royal Bafokeng Organisational Performance Mainmenu_programmes2_up The Royal Bafokeng Business Portal
 
2019/22/07
Water & Sanitation Service Level Agreement with RLM
Project Status:
Approved Active
Project Number: 2236
Project Scope:

To facilitate a water and sanitation Service Level Agreement (SLA) between Rustenburg Local Municipality (RLM) and the Royal Bafokeng Administration (RBA) on behalf of the Royal Bafokeng Nation (RBN). RLM is the official Water Services Authority (WSA) responsible for ensuring that all citizens in its area of jurisdiction have access to basic water supply and sanitation system. By entering into the agreement with RLM, RBA will be formalising its existing arrangement of supplying water and sanitation to RBN community members. This will be achieved through a series of detailed discussions with RLM Management and report back on a regular basis leading to the finalisation and signing of the agreement. 

In scope: 

  • Appointment of professional services to develop business plan;
  • Develop Water Service Provider business plan for RBN;
  • To comply with legislation such particularly the Water Services Act, Municipal Systems Act and the Municipal Finance Management Act;
  • To regularize existing arrangement and improve on it; and 
  • To benefit from grants such as Equitable Share.
Key Focus Area: Governance & Administration
Focus Areas: Public & Community Utilities
Beneficiaries: Traditional leaders/Governance, Community, RBN Employees, South African Government
Regions: Capital Region
Villages: Phokeng
Institutions: Public Services Management
Progress Actual: 33.1 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 8 June 2016
Baseline End Date: Wednesday 11 January 2017
Actual Start Date: Wednesday 8 June 2016
Actual End Date: Wednesday 31 July 2019
Schedule Variance:
-931 days
-429.032 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 2
Resolved: 1
Total: 3
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 
All Rights Reserved | Copyright © 2019 - ROYAL BAFOKENG NATION