Construction of private box lobby
Project Status:
Completed
Project Number: 279
Project Scope:

Construction of new building in designated Plaza parking lot in accordance with the drawings provided by SAPO, incorporating all statutory services by the end of February 2011.

In Scope:

  • Face brick structure with a concrete tile roof to match the existing Plaza building
  • Post boxes will be provided and installed by SAPO

Scope change/additions:

The project completion date has been extended to the 29 June 2011, due to the delay in the delivery of post boxes from the post office officials as they are the ones responsible for the manufacturing of the boxes. Boxes were delivered on 12 April 2011.

Key Focus Area: Public & Community Utilities
Focus Areas: Public & Community Utilities
Beneficiaries: Community
Regions: Capital Region
Villages: Phokeng
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 31 January 2011
Baseline End Date: Wednesday 29 June 2011
Actual Start Date: Monday 10 January 2011
Actual End Date: Wednesday 29 June 2011
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 0
Issues: Unresolved: 0
Resolved: 2
Total: 2
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: