The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/28/03
RBED/CCBSA Youth Entrepreneurship Programme
Project Status:
Completed
Project Number: 2275
Project Scope:

To work in partnership with Coca Cola to identify 45 Royal Bafokeng Youth who want to embark on the business world as entrepreneurs and take them through training process and install a startup container for them in their areas worth R200 000.00 each. The identification process will be conducted through selection and assessment process by creating a registration form that will allow every youth from the age of 24year to 35years. The selected 45 youth will go through a boot camp and learn about business administration and Customer Service. To further manage the immersion of Containers, set up 45 qualified RBN youth and monitor operational process of 45 RBN youth who qualified. The project will start on 1 September 2016 and end on 30 June 2017.

In scope:

  • Preparation phase
  • Awareness & Registration campaign
  • Assessment phase
  • Boot camp/ Training phase
  • Operational phase 1
  • Graduation phase
  • Operation phase 2
  • Monitoring process
  • Project Closure
Key Focus Area: Economic Development
Focus Areas: Education and Skills Development
Beneficiaries: Youth
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Royal Bafokeng Enterprise Development (RBED)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Thursday 1 September 2016
Baseline End Date: Wednesday 31 May 2017
Actual Start Date: Thursday 1 September 2016
Actual End Date: Monday 28 September 2020
Schedule Variance:
-1216 days
-447.059 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
-294.315 %
Risks: 3
Issues: Unresolved: 0
Resolved: 8
Total: 8
Milestones