RBED Youth Business Accelerator Project
Project Status:
Completed
Project Number: 2276
Project Scope:

To establish programmes that will assist the youth owned SMMEs in the database as well as any other Bafokeng youth-owned business, in operating their business more viable and ready for market opportunities. The project will ensure that the businesses are compliant to legislation, access opportunities and they are ready for market through business skills training, business linkages and vendor acquisition assistance. The project has started on the 07th September 2016 and it will end on the 06th of March 2017.

Scope Change request - May 2017: An application for a scope change request has been submitted which will affect the project schedule. The scope change request include increasing the time frame of some of the milestones in the project.

In scope:

  • Improve data and database update
  • Business skills Training
  • Vendor Number Applications
  • Access to business opportunities
  • To reduce youth unemployment through effective entrepreneurship programs
Key Focus Area: Economic Development
Focus Areas: Economic Development
Beneficiaries: Bafokeng SMME's, Youth
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Royal Bafokeng Enterprise Development (RBED)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 7 September 2016
Baseline End Date: Friday 15 December 2017
Actual Start Date: Wednesday 7 September 2016
Actual End Date: Thursday 15 March 2018
Schedule Variance:
-90 days
-19.397 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
-163.698 %
Risks: 3
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: