Monitoring of Electrification Project in Lesung
Project Status:
Completed
Project Number: 2279
Project Scope:

To monitor the construction of the electrification infrastructure project at Tsitsing Village with the aim of connecting about 48 houses. The project is conducted by Eskom in line with Rustenburg Local Municipality’s IDP and Department of Energy's funds. 

Monitoring will be conducted by means of the following:

  1. Ensuring alignment to the Royal Bafokeng Nation Master Plan and or approved cadasters. 
  2. Reviewing and analyzing progress reports and attending site meetings throughout the duration of the project.

The project is anticipated to be concluded by March 2017.

In scope:

  • Consideration of way-eaves;
  • Introducing the project and contractor to the community leaders;
  • Monitoring construction (Attending site meetings and conducting random inspections); and 
  • Project handover.
Key Focus Area: Public & Community Utilities
Focus Areas: Public & Community Utilities
Beneficiaries: Community
Regions: Central Region
Villages: Lesung
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Thursday 23 June 2016
Baseline End Date: Friday 6 January 2017
Actual Start Date: Thursday 23 June 2016
Actual End Date: Monday 6 February 2017
Schedule Variance:
-31 days
-15.736 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: