2024/27/04
2017 Shared Services Satisfaction Survey
Project Status:
Completed
Project Number: 2286
Project Scope:

A project intended to monitor and measure, over time, the progress of shared services group. This will be done by developing a questionnaire that will be administered to all Staff. A report will be compiled on the feedback from the questionnaire results to be disseminated internally. The project completed in January 2018. This is an annual project.

In Scope:

  • Literature review;
  • Interview Shared Services group staff;
  • Design and administer questionnaire; and 
  • Compile report
Key Focus Area: Governance & Administration
Focus Areas: Other
Beneficiaries: RBN Employees
Regions: Capital Region
Villages: Phokeng
Institutions: Research
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 2 October 2017
Baseline End Date: Friday 26 January 2018
Actual Start Date: Monday 2 October 2017
Actual End Date: Monday 2 April 2018
Schedule Variance:
-66 days
-56.897 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 3
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: