2024/30/04
Monitoring of Electrification Project in Mogono
Project Status:
Completed
Project Number: 2304
Project Scope:

To monitor the construction of the electrification infrastructure project at Mogono Village with the aim of connecting approximately 17 houses. The project is conducted by Eskom in line with Rustenburg Local Municipality’s IDP and Department of Energy's funds. 

Monitoring will be conducted by means of the following:

  1. Ensuring alignment to the Royal Bafokeng Nation Master Plan and or approved cadasters. 
  2. Reviewing and analyzing progress reports and attending site meetings throughout the duration of the project.

The project is anticipated to be concluded by March 2017.

In scope:

  • Consideration of way-eaves;
  • Introducing the project and contractor to the community leaders;
  • Monitoring construction (Attending site meetings and conducting random inspections); and 
  • Project handover.
Key Focus Area: Public & Community Utilities
Focus Areas: Public & Community Utilities
Beneficiaries: Community
Regions: North Region
Villages: Mogono
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 12 September 2016
Baseline End Date: Tuesday 28 February 2017
Actual Start Date: Monday 12 September 2016
Actual End Date: Tuesday 28 February 2017
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: