Network development and implementation project
Project Status:
Completed
Project Number: 292
Project Scope:

To implement an infrastructure capable for providing unified communication services i.e.  Voice, data and video to every school, clinic, and community centre and all business parks in the Royal Bafokeng Nation.

In scope:

  • Voice services (Telephone);
  • Data services (Internet and email); and
  • Video services.

Scope change/update:

A project duration extension of 21 weeks from the baseline end date of the project.

Scope change/update:

The following milestones have been excluded from the initial project scope; the milestones will be completed as part of projects that will be registered in the future;

  • Connecting clinics to the network
  • Acquisition of broad band services (ISP)
  • Network equipment configurations
  • Laying an termination of optical fiber
  • Testing
  • Going live
Key Focus Area: Other
Focus Areas: Education and Skills Development, Health and Social Development, Public & Community Utilities, Other
Beneficiaries: Community, RBN Employees
Regions: All Regions
Villages: All Villages
Institutions: Shared Services: IT
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 2 February 2011
Baseline End Date: Tuesday 31 January 2012
Actual Start Date: Wednesday 2 February 2011
Actual End Date: Tuesday 24 January 2012
Schedule Variance:
7 days
1.928 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 0
Issues: Unresolved: 0
Resolved: 8
Total: 8
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found