2024/26/04
Replacement of Lifts at the Civic Center
Project Status:
Completed
Project Number: 2364
Project Scope:

To coordinate the replacement of lifts at the Royal Bafokeng Civic Center as part of the maintenance plan. The project will be carried out by the service provider who will be appointed. The project will start in July and be completed in August 2018. 

In scope:

  • Appoint of the service provider
  • Procurement of imported material
  • Project schedule.
  • Notify staff.
  • Removal of old lifts.
  • Replacements of lift.
  • Commissioning of new lifts for usage.
Key Focus Area: Public & Community Utilities
Focus Areas: Economic Development, Public & Community Utilities, Governance & Administration
Beneficiaries: RBN Employees
Regions: Capital Region
Villages: Phokeng
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 3 July 2017
Baseline End Date: Friday 31 August 2018
Actual Start Date: Monday 3 July 2017
Actual End Date: Tuesday 31 July 2018
Schedule Variance:
31 days
7.311 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 3
Issues: Unresolved: 0
Resolved: 0
Total: 0