2024/20/04
Interim Regional Community Centers
Project Status:
On hold
Project Number: 2376
Project Scope:

To identify sites which have the potential to become community centres within RBN. These structures will be used for commercial purposes. RBN Governance office will be consulted to assist with the identification of these sites and a feasibility study will be done to determine if the identified sites can be used for commercial purposes. The project will be completed in July 2018.

Scope Change request; October 2020.

It has been requested that the last wo milestones of the project be removed, as they will form part of the project that will be implemented by Moumo.

In scope;

  • Consultation with Traditional leadership and Governance leadership.
  • Sites visit
  • Compile a list of sites with the potential to become community centres.
  • Plotting of multipurpose centres on the master plan.
  • Feasibility study for commercial centres.
  • Commercialisation of regional centres.
Key Focus Area: Public & Community Utilities
Focus Areas: Public & Community Utilities, Governance & Administration
Beneficiaries: Community
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Public Services Management
Progress Actual: 88.1 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 5 September 2017
Baseline End Date: Tuesday 10 July 2018
Actual Start Date: Tuesday 5 September 2017
Actual End Date: Wednesday 31 July 2019
Schedule Variance:
-386 days
-125.325 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found