Women Enterpreneurship
Project Status:
Completed
Project Number: 2397
Project Scope:

To identify and train women in Entrepreneurship, and empower them with th skills to use the  Asset Based Community Development model (the leaky bucket). The workshop will equip the beneficiaries with the skills to assist with helping the community to utilise the available assets  and to sustain the economic status in the Bafokeng. After the training the benefiaries will be expected to come up with projects and programmes that will address the identified ills. This in return will contribute towards poverty eradication and unemployment rate. The training will be completed in November 2018.

In scope:

  • Identification of project beneficiaries.
  • Identification and appointment of the service provider.
  • Organize training logistics.
  • Facilitate the training.
  • Do community work
  • Collection of Portfolio of Evidence from the Beneficiaries.
  • Compile the workshop report.
Key Focus Area: Economic Development
Focus Areas: Education and Skills Development, Health and Social Development, Economic Development
Beneficiaries: Women
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Health & Social Development Services (HSDS)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 21 February 2018
Baseline End Date: Monday 2 April 2018
Actual Start Date: Wednesday 21 February 2018
Actual End Date: Monday 26 March 2018
Schedule Variance:
7 days
17.5 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
100.73 %
Risks: 2
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule