Youth Kgotha Kgothe 2018
Project Status:
Completed
Project Number: 2410
Project Scope:

To coordinate a youth Kgotha Kgothe event taking place on Saturday 23 June 2018 at the Civic Centre. To provide a platform where Bafokeng youth can interact with Kgosi and RBN leadership, to seek join solutions in improving the quality of youth programmes in the Royal Bafokeng Nation (RBN). It is also an opportunity for Kgosi to reflect on the goals, achievements and challenges faced in the past year. The event steering committee will assist in ensuring that the project scope is executed and the event is hosted successfully and to facilitate the process of passing resolutions during the meeting. 

In Scope:

  • Establish the committee with a dedicated project managers;
  • A venue big enough for potentially 3000 participants;
  • An effective sound system to communicate to 1000 people, broadcast on 2 big screens in auditorium, PA systems and nine plasma screens for the marquee;
  • Marketing of the event through bulk SMSs, distribution of flyers, and radio announcements (Mafisa FM and Motsweding FM);
  • Transport for every village;
  • Catering (Lunch) for 500 Youth;
  • Bottled water and one drink for lunch per person (500 people);
  • Volunteers to collect waste;
  • Security monitored and maintained during event;
  • Registration of all attendees;
  • Communication's photographer and video broadcasting;
  • Emergency Services available for emergencies;
  • Translator for executive that do not understand Setswana; and 
  • Sign language interpreters.
Key Focus Area: Governance & Administration
Focus Areas: All, Economic Development
Beneficiaries: Youth
Regions: Capital Region
Villages: Phokeng, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega
Institutions: Secretary of Traditional Governance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 4 June 2018
Baseline End Date: Friday 29 June 2018
Actual Start Date: Monday 4 June 2018
Actual End Date: Friday 29 June 2018
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
48.759 %
Risks: 2
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule