The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/23/04
Firebreaks 2018
Project Status:
Completed
Project Number: 2419
Project Scope:

To grade and maintain fire breaks that were installed in RBN. The maintenance of fire breaks is to reduce the occurrence of negative impact of unplanned fires within the RBN areas and to minimise the spread of potential fires within and outside RBN areas. About 957.8 Km of firebreaks will be graded and maintained in 2018. The project will benefit RBN farmers and the community. The project will be completed on the 1st of July 2018. All regions in RBN will be covered.

In scope:

  • Identification and appointment of service providers.
  • Briefing of Service providers
  • Site inspection with service providers
  • Project implementation and monitoring
  • Handover.
Key Focus Area: Environmental Management
Focus Areas: Food Security, Safety and Security, Public & Community Utilities, Environmental Management, Governance & Administration
Beneficiaries: Community, Bafokeng SMME's, Other
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Land use management
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 28 May 2018
Baseline End Date: Monday 16 July 2018
Actual Start Date: Monday 28 May 2018
Actual End Date: Wednesday 10 October 2018
Schedule Variance:
-86 days
-175.51 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
100 %
Risks: 4
Issues: Unresolved: 0
Resolved: 2
Total: 2
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: