2024/24/04
Installation of crush pens 2018
Project Status:
Completed
Project Number: 2420
Project Scope:

To create an enabling environment for Bafokeng stock farmers by erecting crush pens for livestock at their grazing areas. Many local farmers struggle with accessibility to crush pens, thus this project will largely benefit them. A total of 2 crush pens will be erected by end of June 2018. A consultant will be appointed to erect the crush pens. The crush pen will be erected in grazing areas in the Bafokeng regions, and farmers will be expected to share the pens.

In scope:

  • Appointment of contractors;
  • Site inspection with the contractors;
  • Procurement of the crush pens;
  • Erection of the crush pens; and 
  • Site handover.
Key Focus Area: Environmental Management
Focus Areas: Economic Development, Food Security, Public & Community Utilities, Environmental Management
Beneficiaries: Community, Bafokeng SMME's
Regions: Central Region
Villages: Kanana
Institutions: Land use management
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 5 March 2018
Baseline End Date: Friday 29 June 2018
Actual Start Date: Monday 5 March 2018
Actual End Date: Wednesday 19 September 2018
Schedule Variance:
-82 days
-70.69 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
100 %
Risks: 2
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: