Project Status:
Completed
Project Number: 2461
Project Scope:

To monitor the provision of a 1.1 Km paved roads in Rasimone.. The construction is done Rustenburg Local Municipality to ensure that it is of good standard and due process is being followed. The road is being constructed to upgrade existing gravel roads in Rasimone village. This will be accomplished by making use of consultants (Civil engineers) and a contractor with a CIDB grading of no less than six.

Since the road is being constructed on the Royal Bafokeng Nations' (RBN) land, the administration has a vested interest therein. The project manager from the RBN Infraco department will monitor the project through means of receiving and analysing progress reports and attending site meetings throughout the duration of the project that will come to conclusion in October 2018.

In scope:

  • Community awareness and involvement;
  • Approval of road construction and constructions designs;
  • Approval of borrow and spoil sites and rehabilitation plan;
  • Approval of programme of works (Start to Completion);
  • Monitoring construction process (Site meetings including progress reports); and
  • Project handover including as built drawings
Key Focus Area: Public & Community Utilities
Focus Areas: Safety and Security
Beneficiaries: Community
Regions: North Region
Villages: Rasimone
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 5 February 2018
Baseline End Date: Monday 8 October 2018
Actual Start Date: Monday 5 February 2018
Actual End Date: Tuesday 30 April 2019
Schedule Variance:
-204 days
-83.265 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 1
Total: 1