Project Status:
Completed
Project Number: 2478
Project Scope:

To facilitate the process of establishing a deeds office in RBA to house records of each stand within the RBN. Previously there was no place where all records of stands were captured. The project will ensure that all records are captured either physically or electronically into a fully functional system. The project will be completed in August 2020.

Scope Change 07 September 2020: To exclude Stand Audit as one of the project milestones. This milestone will be implemented in a different project related to stand allocation. Only the project schedule will be affected by this change.

In scope:

  • Creation of stand files within the existing Stand Application System
  • Appointment of a data capture
  • Procurement of Equipment
  • Capture the stand information into the files
  • Integration of the stand files with OPMO
  • Stand Audit
  • Monitoring and implementation
Key Focus Area: Governance & Administration
Focus Areas: Public & Community Utilities, Governance & Administration
Beneficiaries: Community
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 15 October 2018
Baseline End Date: Friday 25 September 2020
Actual Start Date: Monday 15 October 2018
Actual End Date: Thursday 31 December 2020
Schedule Variance:
-97 days
-13.643 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 2
Total: 2
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION