The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/18/04
Know your Kgotla (Ikitsi)
Project Status:
Cancelled
Project Number: 2513
Project Scope:

To design 72 profiles of all Makgotla structures in the Bafokeng through a series of interviews across all the regions.  The interviews will be conducted by Bafokeng volunteers who will be paid a stipend.  A set of questions will be created which will be administered by these volunteers.  The project will run from the June to December 2019.

In Scope

  • Questionnaire design;
  • Sourcing permission from Governance;
  • Recruitment if volunteers;
  • Interviews;
  • Data analysis; and
  • Profile compilation.
Key Focus Area: Governance & Administration
Focus Areas: History and Heritage
Beneficiaries: Community
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Office of the Group COO
Progress Actual: 70.5 %
Progress Planned: 100 %
Baseline Start Date: Monday 3 June 2019
Baseline End Date: Wednesday 11 December 2019
Actual Start Date: Monday 3 June 2019
Actual End Date: Monday 1 March 2021
Schedule Variance:
-446 days
-233.508 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
100 %
Risks: 2
Issues: Unresolved: 0
Resolved: 4
Total: 4
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION