2024/28/03
Monitoring the construction of block paved road and storm water structures in Windsor, R-8
Project Status:
Completed
Project Number: 2595
Project Scope:

To monitor the construction of 650m block paved road and storm water structures in Windsor, R-8. The construction is done by Rustenburg Local Municipality to ensure that it is of good standard and due process is being followed. The road is being constructed to upgrade existing roads in Kgale village. This will be accomplished by making use of consultants (Civil engineers) and a contractor with a CIDB grading of no less than six.

Since the road is being constructed on the Royal Bafokeng Nations' (RBN) land, the administration has a vested interest therein. The project manager from the RBN Infraco department will monitor the project through means of receiving and analysing progress reports and attending site meetings throughout the duration of the project that will come to conclusion in November 2019.

In scope:

  • Community awareness and involvement;
  • Approval of road construction and constructions designs;
  • Approval of borrow and spoil sites and rehabilitation plan;
  • Approval of programme of works (Start to Completion);
  • Monitoring construction process (Site meetings including progress reports); and
  • Project handover including as built drawings
Key Focus Area: Public & Community Utilities
Focus Areas: Public & Community Utilities, Environmental Management
Beneficiaries: Community
Regions: Capital Region
Villages: Phokeng
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 4 February 2019
Baseline End Date: Monday 11 November 2019
Actual Start Date: Monday 4 February 2019
Actual End Date: Friday 31 July 2020
Schedule Variance:
-263 days
-93.929 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: