2024/19/04
RBN Operations Room System Development Phase 10
Project Status:
Completed
Project Number: 2601
Project Scope:

To further develop the OPMO system software in order to improve the user experience, increase or improve efficient and effective management of project and programmes and to address identified system needs in the RBN.  The system development partner will be instructed to develop the new features in accordance to the specifications provided by the RBN OPMO.  The new features are expected to be live in August 2019.

In scope:

  • Development of:
    • Development of the quick programme update functionality
    • Development of the new tabs in the home page
    • Re arrangement of the tabs in the home page to accommodate new tabs
  • Manage the development of software solutions
  • Test new features
  • Roll-out of new features
Key Focus Area: Governance & Administration
Focus Areas: Governance & Administration
Beneficiaries: RBN Employees, Senior Citizens
Regions: Capital Region
Villages: Phokeng
Institutions: Office of the Group COO
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 5 February 2019
Baseline End Date: Monday 5 August 2019
Actual Start Date: Tuesday 5 February 2019
Actual End Date: Thursday 31 October 2019
Schedule Variance:
-87 days
-48.066 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 5
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule