Construction of two classroom blocks at Motsitle Primary of approximately 292m2 floor area and a staff-room at Mmanape High of approximately 130m2 floor area; to be completed in February 2010.
Key Focus Area:
Education and Skills Development
Focus Areas:
Education and Skills Development, Public & Community Utilities
Beneficiaries:
Community, Youth
Regions:
All Regions, Capital Region, North Region
Villages:
Kgale, Luka
Institutions:
Infrastructure Maintenance
Progress Actual:
100 %
Progress Planned:
100 %
Baseline Start Date:
Wednesday 7 October 2009
Baseline End Date:
Friday 12 February 2010
Actual Start Date:
Wednesday 7 October 2009
Actual End Date:
Thursday 18 March 2010
Schedule Variance:
-34 days -26.563 %
Approved Total Budget:
Hidden
Total Expenditures:
Hidden
Estimated to Complete:
Hidden
Total at Completion:
Hidden
Budget Variance:
Hidden 0 %
Risks:
2
Issues:
Unresolved: 0 Resolved: 0 Total: 0
Addition of staffrooms and classrooms at Mmanape high and Motsitle primary