Firebreaks-2020
Project Status:
Completed
Project Number: 2609
Project Scope:

To grade and maintain fire breaks that were installed in RBN. The maintenance of fire breaks is to reduce the occurrence of negative impact of unplanned fires within the RBN areas and to minimise the spread of potential fires within and outside RBN areas. About 1207.70 Km of firebreaks will be graded and maintained in 2019. The project will benefit RBN farmers and the community. The project will start in 2 June 2020 and is planned to complete in August 2020. All regions in RBN will be covered.

Scope change request, September 2020: Increase the project schedule.

In scope:

  • Identification and appointment of service providers.
  • Briefing of Service providers
  • Site inspection with service providers
  • Project implementation and monitoring
  • Handover.
Key Focus Area: Environmental Management
Focus Areas: Food Security, Safety and Security, Public & Community Utilities, Environmental Management, Governance & Administration
Beneficiaries: Community, Bafokeng SMME's, Other
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Land use management
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 2 June 2020
Baseline End Date: Friday 30 October 2020
Actual Start Date: Tuesday 2 June 2020
Actual End Date: Friday 26 February 2021
Schedule Variance:
-119 days
-79.333 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 5
Issues: Unresolved: 0
Resolved: 2
Total: 2
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found