Project Status: |
Approved Active |
Project Number: |
2609 |
Project Scope:
|
To grade and maintain fire breaks that were installed in RBN. The maintenance of fire breaks is to reduce the occurrence of negative impact of unplanned fires within the RBN areas and to minimise the spread of potential fires within and outside RBN areas. About 1207.70 Km of firebreaks will be graded and maintained in 2019. The project will benefit RBN farmers and the community. The project will start in 2 June 2020 and is planned to complete in August 2020. All regions in RBN will be covered.
Scope change request, September 2020: Increase the project schedule.
In scope:
- Identification and appointment of service providers.
- Briefing of Service providers
- Site inspection with service providers
- Project implementation and monitoring
- Handover.
|
Key Focus Area: |
Environmental Management |
Focus Areas: |
Food Security, Safety and Security, Public & Community Utilities, Environmental Management, Governance & Administration |
Beneficiaries: |
Community, Bafokeng SMME's, Other |
Regions: |
All Regions |
Villages: |
Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages |
Institutions: |
Land use management |
Progress Actual: |
61.1 % |
Progress Planned: |
100 % |
Baseline Start Date: |
Tuesday 2 June 2020 |
Baseline End Date: |
Friday 30 October 2020 |
Actual Start Date: |
Tuesday 2 June 2020 |
Actual End Date: |
Friday 26 February 2021 |
Schedule Variance: |
-119 days -79.333 %
|
Approved Total Budget: |
Hidden |
Total Expenditures: |
Hidden |
Estimated to Complete: |
Hidden |
Total at Completion: |
Hidden |
Budget Variance: |
Hidden 0 %
|
Risks: |
5 |
Issues: |
Unresolved: 1 Resolved: 1 Total: 2
|
|