2024/25/04
Server visualization
Project Status:
Completed
Project Number: 2617
Project Scope:

To coordinate the process of visualising the RBN server room.  The reason for the process is to  reduce hardware costs, faster server provisioning and deployment, to greately improve disaster recovery, significant energy cost savings and increase productivity. The proce of implementation includes procurement of hardwares and softwares and followed by implementation. The is scheduled to start in October and be completed by end December 2020.

In scope:

  • Development of a project plan;
  • Procurement of Hardware and softwares;
  • Implementation; and
  • Project handover/completion.
Key Focus Area: Governance & Administration
Focus Areas: All
Beneficiaries: RBN Employees
Regions: Capital Region
Villages: Phokeng
Institutions: Shared Services: IT
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Thursday 1 October 2020
Baseline End Date: Wednesday 16 March 2022
Actual Start Date: Thursday 1 October 2020
Actual End Date: Friday 10 February 2023
Schedule Variance:
-331 days
-62.335 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 3
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found