2024/28/03
Monitoring the construction of block paved road and storm water structures in Robega
Project Status:
Completed
Project Number: 2622
Project Scope:

To monitor the construction of 950m block paved road and stormwater structures in Robega. The construction is done by RBplats to ensure that it is of a good standard and due process is being followed. The road is being constructed to upgrade existing roads in Robega village. This will be accomplished by making use of consultants (Civil engineers) and a contractor with a CIDB grading of no less than six.

Since the road is being constructed on the Royal Bafokeng Nations' (RBN) land, the administration has a vested interest therein. The project manager from the RBN Infraco department will monitor the project through means of receiving and analysing progress reports and attending site meetings throughout the duration of the project that will come to conclusion in September 2021.

In scope:

  • Community awareness and involvement;
  • Approval of road construction and constructions designs;
  • Approval of borrow and spoil sites and rehabilitation plan;
  • Approval of programme of works (Start to Completion);
  • Monitoring construction process (Site meetings including progress reports); and
  • Project handover including as built drawings
Key Focus Area: Public & Community Utilities
Focus Areas: Public & Community Utilities, Environmental Management
Beneficiaries: Community
Regions: North Region
Villages: Robega
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Saturday 8 May 2021
Baseline End Date: Wednesday 8 September 2021
Actual Start Date: Saturday 8 May 2021
Actual End Date: Monday 17 January 2022
Schedule Variance:
-131 days
-106.504 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION