2024/30/04
Acquisition of Drone Technology
Project Status:
Approved Active
Project Number: 2635
Project Scope:

To facilitate the process of procuring drone in order to enhace Security services in RBN. The aim The aim of the project is to establish the drone technology to conduct monitoring patrol in RBN Land and Properties that will also provide support of aerial surveillance to the ground operators. The project is planned to start in February 2022 and is due to complete end of 2022.

In scope

  • Procurement process
  • Appointment of the service provider
  • Training of the pilots 
  • Demonstration of the drones to the Senior officials
  • Signing off of the hardware 
  • Procurement of the hardware
  • Monitoring
  • Completion of the project.
Key Focus Area: Safety and Security
Focus Areas: Education and Skills Development, Economic Development, Safety and Security, Governance & Administration
Beneficiaries: Community, RBN Employees
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Protective Services
Progress Actual: 90.9 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 1 February 2022
Baseline End Date: Thursday 17 November 2022
Actual Start Date: Tuesday 1 February 2022
Actual End Date: Friday 31 May 2024
Schedule Variance:
-561 days
-194.118 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 2