Upgrading of security infrastructures (Cameras and Perimeter Fences) at various water management plants, Coetzee Farm, Coetzee Farm extension, Lemenong, and other RBN facilities (EMRS Facilities and Protective Services) to address the shortcomings of the existing systems and update capabilities to allow for future expansion and enhancement of security. The project is expected to run from June 2024 to February 2025. A service provider will be appointed for the implementation of the identified solution.
In scope:
Coetzee Farm and Extension
- Installation of Clear Vu perimeter fencing and CCTV
Lemenong 1 & 2:
- Installation of Clear Vu perimeter Fencing
- Upgrade of CCTV cameras
EMRS:
-Upgrading of CCTV and Access control
Protective Services:
-Upgrading of Operations Room
Scope Extension (17 March 2025):
The scope has been extended to include Phokeng North, Phokeng Central, Lebone II and Legato.