2024/25/04
Pressure control valves maintenance
Programme Status:
Approved Active
Programme Number: 630
Programme Executive Summary (Scope):

To maintain pressure control valves at the sixteen reservoirs and within the network reticulation systems for all RBN villages, to minimise pipe bursts, leaks and also to maintain the pipes regulated pressure for optimal life span.

In scope:

  • Clean out pressure valve;
  • Reset pressure valve; and
  • Replacement of faulty parts and/or valves.
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Community
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Infrastructure Maintenance
Baseline Start Date: Tuesday 3 January 2012
Actual Start Date: Tuesday 3 January 2012
Approved Annual Budget: Hidden
Budget Variance:
2024 Year to date budget: Hidden
2024 Year to date expenses: Hidden
2024 Budget variance to date: 0 %
2024 Percentage of annual budget spent: 0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 7
Total: 7