Projects |
To coordinate the establishment of animal pound/feedlot in Bafokeng
area and to produce high quality livestock, to nourish people in
Bafokeng and neighbouring communities. This is a joint project between
Royal Bafokeng and Rustenburg Local Municip...
Open Issues: 0
Duration: 254 days
Project Manager: Gillian Senne
|
Internal Risks: 0
External Risks: 3
Budget: Hidden
Percentage Progress: 42.6 %
|
|
To apply for accreditation for advanced life support in order to bill
for services rendered and source revenue to the RBN. The process will
entail information gathering from various stakeholders and submitting
the application at the Board of healt...
Open Issues: 0
Duration: 820 days
Project Manager: Thabo Mogale
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 83.6 %
|
|
To install sewer reticulation in all RBN villages as per designs done
in previous projects (Phokeng, Luka Mogono, Robega, Rasimone, Chaneng
and Mafenyane (Western villages) including bulk out fall sewer line
and sewer treatment plant. ...
Open Issues: 0
Duration: 30 days
Project Manager: Sandra Kekae
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 0 %
|
|
To coordinate a regional youth Community Capacity Enhancement (CCE)
dialoque in RBN. The objective is to make a follow up regarding the
issues and concernes raised by youth during RBN youth Kgothakgothe
that was held on the 2nd of July 2016. The p...
Open Issues: 1
Duration: 47 days
Project Manager: Gladys Pikanisi
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 29.2 %
|
|
To develop a Monitoring and Evaluation guideline that will assist in
measuring the impact of youth in school program implemented in RBN
schools. This guideline will be used by the programme implementers in
selected RBN schools to administer and tr...
Open Issues: 0
Duration: 223 days
Project Manager: Gabriel Lenkwe
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 5.8 %
|
|
To identify sites which have the potential to become community
centres within RBN. These structures will be used for commercial
purposes. RBN Governance office will be consulted to assist with the
identification of these sites and a feasibility st...
Open Issues: 0
Duration: 308 days
Project Manager: Nthebe Ntsimane
|
Internal Risks: 1
External Risks: 0
Budget: Hidden
Percentage Progress: 88.1 %
|
|
To coordinate RBA/RBN clean-up campaign. The objective of the
campaign is to encourage employees to get involved and help keep the
villages and sorroundings tidy. Employees from all entities will be
invited to participate in th capaign by tidying ...
Open Issues: 0
Duration: 289 days
Project Manager: Reotshepile Tlhapane
|
Internal Risks: 1
External Risks: 1
Budget: Hidden
Percentage Progress: 4 %
|
|
To design, develop and implement a Loyalty Programme for RBN
residents that will promote good cooperate and social behaviour in
support of Plan 35. The objective of the project is to better the
standard of living for all individuals by improving t...
Open Issues: 0
Duration: 368 days
Project Manager: Ororiseng Nameng
|
Internal Risks: 1
External Risks: 1
Budget: Hidden
Percentage Progress: 15.3 %
|
|
The focused ED approach entails the selection of a number of high
growth potential SMME and providing customised development
interventions such as technical mentoring business mentoring and
coaching, Bankable business plan, facilitate access to fu...
Open Issues: 0
Duration: 1111 days
Project Manager: Dan Seripe
|
Internal Risks: 0
External Risks: 4
Budget: Hidden
Percentage Progress: 80.2 %
|
|
To facilitate the process of submitting a request to approve RBN
heritage sites to be declared as local sites within the RBN through
the Land Committee. Once the sites are declared around the RBN,
Provincial and National heritage agencies will be ...
Open Issues: 0
Duration: 140 days
Project Manager: Khumo Molobye
|
Internal Risks: 1
External Risks: 1
Budget: Hidden
Percentage Progress: 34.5 %
|
|
To coordinate the supply and installation of 800m of concrete
palisade fence around the new centralized cemeteries in Luka as one of
the RBN villages. The project started in November 2018 and is planned
to be completed in May 2019. The aim is to p...
Open Issues: 0
Duration: 208 days
Project Manager: Collen Mekgwe
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 75.9 %
|
|
The former TEBA buildings and site have been unoccupied for two
years. This project will undertake a basic renovation of these
premises with the view to establishing the RBI STEAM centre there in
2020.
The scope of work will include:
- Strip...
Open Issues: 0
Duration: 125 days
Project Manager: Simon Hartley
|
Internal Risks: 4
External Risks: 0
Budget: Hidden
Percentage Progress: 31.6 %
|
|
Oral History Collection 2019...
Open Issues: 0
Duration: 31 days
Project Manager: Khumo Molobye
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 0 %
|
|
Heritage Route: Protection of Heritage Sites (Nape Hill and Malejane
Hill)...
Open Issues: 0
Duration: 31 days
Project Manager: Khumo Molobye
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 0 %
|
|
To equip schools with reading material in order to enable learners to
maximise their academic potential by 31 July 2009.
...
Project Status: Completed
Open Issues: 0
Duration: 731 days
Project Manager: Denise Kunstler
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
To undertake a Strategic Environmental Assessment (SEA) which will
facilitate decision-making in order to achieve environmental
sustainability by 29 November 2009....
Project Status: Completed
Open Issues: 0
Duration: 820 days
Project Manager: Mzila Mthenjane
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To establish and implement a hydroponic system to produce vegetables
by 30 November 2009. ...
Project Status: Completed
Open Issues: 0
Duration: 637 days
Project Manager: Motlapele Tumagole
|
Internal Risks: 1
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
Leadership Development project (LD) is a means to adapt to Bafokeng
traditional system. In fact, LD constitutes a backbone of all
activities undertaken in the RBN from the fact that it is a forum for
interaction between the local authorities and t...
Project Status: Completed
Open Issues: 0
Duration: 899 days
Project Manager: Tshepiso Morei
|
Internal Risks: 1
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
To renovate and refurbish Phokeng Health Centre, Luka Clinic & Chaneng
clinics in the RBN by Apr 2010....
Project Status: Completed
Open Issues: 0
Duration: 760 days
Project Manager: Meisie Mabothe
|
Internal Risks: 6
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To apply for Environmental authorisation through environmental
consultants for the construction of sewer pipelines in Lefaragetlhe/
Rasimone/ Chaneng sewer treatment plant.
IN SCOPE:
* Identification of Environmental Consultants;
* Geohyd...
Project Status: Completed
Open Issues: 0
Duration: 456 days
Project Manager: Reotshepile Tlhapane
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
|